Execution of water transmission line and Pump station of Khouzestan steel company green bel


PROJECT


Execution of water transmission line and Pump station of
Khouzestan steel company green belt.

CLIENT

Iranian Mines & Mining Industries Development & Renovation (IMIDRO), Khouzestan steel company

YEAR 

2007-2008

STATUS

Completed

Project Duration

12  Month


Project Description:

Execution of water transmission line and Pump station of Khouzestan steel company green area.

The project is mainly included of below sub projects:

Pump station:

Execution of pump house, Supply of all mechanical and electrical equipment and bulk materials and execution of all civil and electromechanical works. provision of transformers and switch gears and crane.

 

The water transmission line:

Execution of about 10 Km poly ethylene pipes

DN= 630mm and relevant valves and construction of relevant valve pits.

 

Construction of suction basin:

Concrete suction basin and execution of relevant collector with 24” CS pipes for about 250 m length.

 

Execution of power transmission line:

Power transmission ine and relevant sleeves and concrete boxes and manholes.